Tonny Staunsbrink
2002-10-23 12:01:58 UTC
Hi all
I am new to list and have joined because i would like to share a few
thoughts about what i think could make a good project even better.
I been using mrproject a little and have been wondering about the
handling of tasks.
All tasks in mrproject has a certain duration. This duration however is
static no matter how many work ressources you assign to a task (and i
think three people ought to be faster than one - not always, but most of
the time ;-) ). I think updating the duration for a task manually is
tedious. It is something the application should help with.
Is there somebody on the list with an opinion on this? Is there a reason
for having manual updates?
If automatic duration calculation is a wanted feature it is something i
would like to have look into.
Regards
Tonny Staunsbrink
<***@ruc.dk>
I am new to list and have joined because i would like to share a few
thoughts about what i think could make a good project even better.
I been using mrproject a little and have been wondering about the
handling of tasks.
All tasks in mrproject has a certain duration. This duration however is
static no matter how many work ressources you assign to a task (and i
think three people ought to be faster than one - not always, but most of
the time ;-) ). I think updating the duration for a task manually is
tedious. It is something the application should help with.
Is there somebody on the list with an opinion on this? Is there a reason
for having manual updates?
If automatic duration calculation is a wanted feature it is something i
would like to have look into.
Regards
Tonny Staunsbrink
<***@ruc.dk>